Supreme Court hears appeal against Delhi High Court's interim order on principal amount payment
- Case
- M/S Royal Construction Company Pvt. Ltd vs M/S National Projects Construction
- Bench
- Vikram Nath, J.
- Citation
- Civil Appeal @ SLP (C) No. 14005 of 2026
- Decided
- Statutes
- Constitution of India — s.134-A, s.133(1)(a)
In M/S Royal Construction Company Pvt. Ltd vs M/S National Projects Construction, the Supreme Court on 2026-10-28 heard an appeal against an interim order of the Delhi High Court. The High Court had granted liberty to parties to seek clarification from the Supreme Court regarding the non-disclosure of principal amount payment in 2009, which was relevant to a substantial question of law framed under Article 134-A read with Article 133(1)(a) of the Constitution of India.
Ratio Decidendi · Legal Principle Established
The Supreme Court granted leave to appeal an interim order of the High Court which sought clarification from the Supreme Court itself regarding a fact not brought to its notice during an earlier consideration of a substantial question of law.
Practice & Procedural Impact for Advocates
Advocates should ensure all material facts, especially those concerning payments, are brought to the court's attention at the earliest opportunity. Litigants may face further proceedings if material facts are not disclosed in prior stages, potentially leading to appeals against interim orders seeking clarification.
Key Legal Takeaways
- 1The Supreme Court granted leave to appeal an interim order.
- 2The Delhi High Court's interim order sought clarification from the Supreme Court.
- 3The clarification concerned the non-disclosure of principal amount payment in 2009.
- 4The issue related to a substantial question of law under Article 134-A read with Article 133(1)(a) of the Constitution.